Prof. Suzan Allaham is an accomplished engineering educator, design engineer, and project manager with over 25 years of experience in engineering education, industry, and consultation. She is an Assistant Teaching Professor at Arizona State University and a Ph.D. candidate in Engineering Education Systems and Design (EESD). Her extensive career spans seven countries, where she has worked on major engineering projects with global organizations such as The World Bank, Shell Global, and Eesti Energia.
As an accredited engineer in Jordan, and UAE, Prof. Allaham has led and coordinated more than 30 national and international projects, including mega infrastructure developments like the Mujib Dam in Jordan. She has worked with top decision-makers, overseeing project planning, design, financial management, and implementation.
Commitment to Engineering Education & Student Success
Prof. Allaham is a certified educator through the Association of College and University Educators (ACUE), with over a decade of teaching experience at university and community college levels. She specializes in curriculum design, active learning methodologies, and interdisciplinary engineering education. Her teaching philosophy emphasizes hands-on learning, and real-world engineering applications, through integrating project-based learning (PBL) pedagogy. She contributed to establishing a million-dollar maker space to bridge the gap between academia and professional practice.
Vision
Prof. Allaham is dedicated to empowering future engineers by nurturing an entrepreneurial mindset, encouraging open dialogue, and promoting diversity within STEM. She inspires students to think critically, embrace creativity, and approach challenges with innovation and initiative. Prof. Allaham’s ultimate vision is to shape engineers who are not only technically proficient but also entrepreneurial thinkers, poised to drive transformative change and make a lasting impact on the world.
- Ph.D., Engineering Education Systems and Design, Arizona State University, 2028.
- M.A., Civil Engineering, The University of Jordan, 2002.
- S. Allaham and J. Bekki, "WIP: Exploring Cultural Assets and Their Influence on Fostering a Sense of Belonging Among Women in the Middle East and North Africa (MENA) Region," 2024 IEEE Frontiers in Education Conference (FIE), Washington, DC, USA, 2024, pp. 1-5, doi: 10.1109/FIE61694.2024.10892851. keywords: {Engineering profession;Africa;Color;Cultural differences;Global communication;Interviews;Faces;STEM;IEEE Regions;Gender issues;Women of Color;STEM;Belonging;Cultural Assets;MENA;Engineering Education;Cultural Practices;Religious Beliefs;Societal Values},
- “Waste Management in Dhaka, Bangladesh: A Plan to End Domestic Waste Pollution on the Primary and Secondary Level”, South Mountain Community College and Basis School-Ahwatukee, 2021-USA.
- “Tensile Testing”, South Mountain Community College, 2015-USA
- “LEED Gap Analysis – Respecting Diversity Through the Localization of the LEED Rating System in the Region – Jordan as a Case Study”, JGBC, year 2012-Jordan
- “Water Users’ Associations in Jordan Valley, a Success Story for PPP”, in the Sixth IWA Conference, Efficient 2011, year 2011-Deadsea, Jordan
- “Raising Water Use Efficiency in Jordan Valley Farms”, in the sixth IWA Conference, Efficient 2011, year 2011-Jordan
- “Impacts of Applying the Cost Recovery Policy on the Socio-Economic and Marketing Trends in the Jordan Valley”, in the First Arab Water Week, year 2010-Jordan
- “Introducing the Cost Recovery Component as a Potential Factor for the Selection Mechanism of WEAP Model; the case of North and Middle Jordan Valley”, in the First Arab Water Week, year 2010-Jordan
Courses
2025 Summer
Course Number | Course Title |
---|---|
FSE 100 | Introduction to Engineering |
CON 223 | Strength of Materials |
CON 223 | Strength of Materials |
2025 Spring
Course Number | Course Title |
---|---|
EGR 101 | Found of Eng Design Proj I |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
2024 Fall
Course Number | Course Title |
---|---|
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
CON 598 | Special Topics |
CON 494 | Special Topics |
2024 Summer
Course Number | Course Title |
---|---|
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
CON 223 | Strength of Materials |
2024 Spring
Course Number | Course Title |
---|---|
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 100 | Introduction to Engineering |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 100 | Introduction to Engineering |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 404 | EPICS Gold: EPICS in Action |
CON 598 | Special Topics |
FSE 100 | Introduction to Engineering |
2023 Fall
Course Number | Course Title |
---|---|
FSE 404 | EPICS Gold: EPICS in Action |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 104 | EPICS Gold I |
ASU 101-CAI | The ASU Experience |
ASU 101-CAI | The ASU Experience |
ASU 101-CAI | The ASU Experience |
CON 598 | Special Topics |
CON 494 | Special Topics |
2023 Summer
Course Number | Course Title |
---|---|
CON 221 | Applied Statics |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
CON 221 | Applied Statics |
2023 Spring
Course Number | Course Title |
---|---|
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 100 | Introduction to Engineering |
CON 494 | Special Topics |
CON 598 | Special Topics |
2022 Fall
Course Number | Course Title |
---|---|
FSE 104 | EPICS Gold I |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 404 | EPICS Gold: EPICS in Action |
FSE 104 | EPICS Gold I |
FSE 104 | EPICS Gold I |
FSE 100 | Introduction to Engineering |
FSE 100 | Introduction to Engineering |
FSE 404 | EPICS Gold: EPICS in Action |
- Continuous Improvement and Innovation Piller Award, South Mountain Community College, Spring 2022.
- Outstanding Adjunct Award, South Mountain Community College, Spring 2021.
- Environment Consultant , Jordan Engineers Association, Fall 2012.
- Effort Recognition, Ministry of Water and Irrigation, Jordan Valley Authority
Several recognition letters and trophies from schools/organizations for volunteer work in environmental awareness
- US Green Building Council (USGBC), Arizona Chapter 2015 - Present
- American Muslim Women’s Associate of Arizona (AMWA), Refugee Director and Board Member 2016 - Present
- Member of Sustainable Design Steering Committee, Jordan Engineering Association 2013-2015
- Jury member in Hashemite Fund for Human Development (JOHUD) for Jo-Green Competition 2013 - 2014
- Founder of Jordan Green Building Council and Board Member 2011 - 2016
- Arab Countries Water Utilities Association, ACWUA 2011 - 2015
- Environment Friend Society- UAE 2002 - 2005
- Attended and participated in more than 40 conferences all around the world 2002 - 2020
Academic Advisor :
- Global Career Network at Arizona State University
- Print-A-Smile at ASU.
- Muslims in Medicine at ASU
- Syrian Student Association.
- Jordanian Students Association at ASU
- Saudi Students Club at ASU
Grand Challenges Scholars Program ( GCSP) Reviewer.
Design &Tender Documents Preparation of the Force-main From East Zarqa Pump Station to AsSamra WWTP, Jordan, 2014 – 2015
Position : Project Manager
Funding Agency : Saudi Funds
Client :Ministry of Water and Irrigation
Project Features
The main objective of the Project is the design of a new pipeline from (EZPS) to AS-Samra and this includes:
- Provide sufficient capacity to transfer the expected flow from (EZPS) to ASSamra(WWTP) due to increased capacity of the pump station in a safe and economic condition.
- Proved redundancy in the system to allow refurbishment of the existing pipelines from (EZPS) to AS-Samra (WWTP).
Activities
- Manage the Project
- Preparation of Tender Documents
- Managing the services of different suppliers including the Topo Survey and Geotechnical investigation.
Study, Design, Preparation of Tender Documents and Infrastructure Rehabilitation for the Old Sana’a City, Yemen, 2013 – 2015
Position : Project Manager
Funding Agency : Arab Fund for Economic and Social Development
Client : Sana’a Water and Sanitation Local Corporation (SWSLC)
Project Features
The overall objective of the project is to prepare a comprehensive study and design along with the Tender Documents for the required work and the preventive actions to rectify the existing situation at the old city of Sana’a.
Preparation of designs and recommend system of high standards and high factor of safety for the Infrastructure (Sewerage Network and Water Supply) to insure the durability and long life operation. The work is also to include contractors prequalification.
Activities
- Manage the Project
- Conducting the required special studies
- Preparation of Tender Documents
- Pre-contract Service
- Managing the services of different suppliers including the Topo Survey and Geotechnical investigation.
Aseer Wastewater Treatment Plant Design And Studies Phase II, KSA, 2013 – 2015
Position : Project Manager
Client :General Directorate of Water -Aseer Region
Project Features
The Project is to consider design services for Wastewater treatment plants (WWTP) in a number of governorates and centers of Aseer (phase II). There are 11 areas under this Project. These areas under the Project design scope of work are Thahban Center, Omoq Center, Saeedah AL Sawalha Center, Ethnain Balasmar Center, North Al Nammas Phase I, North Al Nammas Phase II, North Al Nammas Phase II, North Al Nammas Phase IV, North Al Nammas Phase V, Wadi bin Hashbal Center and Al Raboua’a Center,
Activities
- Manage the Project Activities
- Study the possibility of phasing for the construction works required for each WWTP and in each area.
- Introduce alternatives for the required process in accordance to the most recent systems and technologies in the field of wastewater treatment process.
- Prepare alternatives description, features and comparison within the preliminary design stage.
- Study possible solutions and ways to reuse effluent water.
- Preparation of environment impact assessment (EIA) report for each WWTP.
- Preparation of detailed designs and tender documents
Addendum to the Environmental and Impact for oil shale mining and oil shale fired power production in Jordan, 2014-2015
Position: Water resources and hydrology engineer
Client: Eesti Energia
Project Features:
Based on the approved EIA for the project in 2013, new changes on the project are required as a result of the negotiations between the project owner and government of Jordan, which are: 1) project area extension options; and 2) potential increase in water consumption. Which is triggered the need for a re-assessment.
Activities:
Preparing water resources baseline and assessment.
Supervision on the construction of watercourse for Hishkaro River and Main Sewrage Collector Project Dohuk – Kurdistan Iraq (2014- 2015).
Position: Project manager and hydrological Expert
Client: Dohuk Governorate
Project Features
The project is classified as a supervision project with main role of redesign the channel of Hishkaro river hydrologically and hydraulically since the original hydraulic and hydrological detailed design is not meet the flood within the project location.
Activities
Review the contractor hydrological and hydraulic reports in addition to the role of the project manager.
Hydrological and Hydraulic assessment study for 40 MW Solar Power Plant Projects at Ma’an MDA – Jordan (2014).
Position: Hydrology Expert
Client: Scatec Solar
Project Features
The provided services includes reviewing and evaluating the pervious hydrological studies then prepare the most feasible hydrological alternatives and recommendations finally develop plans and profiles for the selected hydrological alternative for four plots with Ma’an Development Area.
Activities
Preparing all required reports.
Environmental and Social Impact Assessment for Zubair, Al Rafidiya, Mishref Hammar gas compression Station, Basra, Iraq (2014- 2015)
Position:
Hydrologist and physical Assessment
Client: Basrah Gas Company –BGC/Shell
Project Features
The assignment aims at carrying out Comprehensive Environmental and Social Impact Assessments for the Construction and expansion three gas compression stations at Basra Governorate.
Activities
Coordinating all work activities between the project's four key experts and managing all aspects related to the implementation of the work activities, starting from field visits to drafting specialized studies and preparing final reports.
Environmental and Social Impact Assessment for 21 MW Solar Power Plant in Ma’an, Jordan (2014)
Position: Technical Team Leader and Hydrologist
Client: Falcon Ma'an Solar Power
Project Features
The assignment aims at carrying out Comprehensive Environmental and Social Impact Assessments for the Construction of PV Solar Power Plant in Ma’an, Jordan. The plant aims at generating 21 MWh of solar power.
Activities
Preparation of baseline, stakeholders engagement plan, and Physical assessment and
Environmental and Social Impact Assessment for Three Solar Power Plants in Ma’an, Jordan (2014)
Position:Technical Team Leader
Client: Adenium Energy Capital
Project Features
The assignment aims at carrying out Comprehensive Environmental and Social Impact Assessments for the Construction of Three PV Solar Power Plants in Ma’an, Jordan. Each plant aims at generating 10 MWh of solar power.
Activities
Coordinating all work activities between the project's four key experts and managing all aspects related to the implementation of the work activities, starting from field visits to drafting specialized studies and preparing final reports.
Environmental Impact Assessment (EIA) for the for Rehabilitation of Marine Terminal at Umm Qasr, Iraq (2013 -2014)
Position: Water Resources Engineer and Air Quality expert
Client: Shell
Project Features
Shell Iraq is planning to rehab the three jetties in the Um Qasr city, the rehabilitation include a grudging process
Activities
Preparation of baseline, stakeholders engagement plan, and Physical assessment
Environmental Impact Assessment (EIA) for the Aqaba Oil & LPG Storage Terminal , Jordan (2013 -2014)
Position: Hydrologist, Water Resources Engineer, and Air Quality expert
Client: ILF Consulting Engineers
Project Features
the study is an EIA for project for engineering, material procurement, construction, painting, testing and commissioning of a crude oil and liquefied petroleum gas terminal with 131,280 cubic meter storage capacity, situated some 22 kilometres from Aqaba at the south.
Activities
Preparation of baseline
Sultani Oil Shale Conceptual Design, Jordan (2013 )
Position: Project Manager and Wastewater collection system Designer
Client: ShaleEnergy
Project Features
The project is a conceptual master planning for a mining area including the infrastructure Roads, and water, wastewater, firefighting. Network in addition to water and wastewater treatment plants
The project contains three parts, the processing area, the mining area and the township.
Activities
Preparation of Wastewater conceptual Design Report and Drawings in addition to the project management tasks
Energy, Water, Paper , and Telecommunication Assessment Study, Jordan (2013 – 2015)
Position: Project Manager and Water Auditor
Client: Central Bank of Jordan
Project Features
The central bank is moving toward to be more sustainable thrugh the assessment for energy, water, Paper and Telecommunication facilities within the bank buiidings and branches in Aqaba and Irbid. The assessment studied the procedure in order to reduce the overall consumption.
Activities
Preparation the Water assessment Report, Boqs, and Specs in addition to the project management tasks
Feasibility Study for Modernisation of the Water Supply and Wastewater Management Systems of Yarmouk Water, (2012-2013)
Position: Social specialist
Client: WS Atkins International Ltd (Funded by the European Bank for Reconstruction and Development (EBRD)
Project Features:
Preparation of a feasibility study of Yarmouk Water Company (the Company), which shall include identification and a detailed assessment of the Priority Investment Programme (PIP) on the rehabilitation and upgrade of water and wastewater systems, that will cover the period of up to 3 years, (i.e. the financing period), detailed financial analysis of the Company, as well as preparation of an overall procurement and project implementation plans, and undertaking environmental and social due diligence
Activities:
Preparation of Stakeholder Engagement Plan as per EBRD requirements.
Environmental and Social Impact Assessment Framework Semel – Ibrahim Al Khalil Road Corridor, Kurdistan Iraq (2013)
Position: Water Resources Engineer
Client: The Ministry of Construction and Housing / General Directorate of Roads and Bridges in Duhok and World Bank– Kurdstane -Iraq
Project Features
Upon the requirements of World Bank The client is preparing the ESIAF in order to finance the construction of the third segment of the corridor by the World Bank.
Activities
Preparation of EIA baseline and
Aden & Hodeidah Hospitals Waste Management Plan, Yemen (2012)
Position: Environment Technical Leader
Client: Ministry of Water and Environment - Yemen
Project Features
The study is to prepare medical and domestic solid waste management plan for two hospital s in Yemen , Aden Medical city and Hodeidah Hospitals.
Activities
Preparation of waste management plan
Environmental, Social and Health Impact Assessment (ESHIA) for the Appraise Phase Activities, Jordan (2013)
Position: Senior Environmental Engineer
Client: Jordan Oil Shale Company (JOSCO) – Subsidiary of Shell
Project Features
JOSCo is moving towards concluding its Assessment phase exploration activities and entering the Appraise phase by May 2013 as part of the Oil Shale Concession Agreement (OSCA). Therefore, there is a need to conduct an ESHIA study, to identify potential environmental, social and health impacts.
Activities
Preparation of Preliminary and Final Terms of Reference and EIA baseline
Resettlement Implementation Services for Water and Waster Project in Zarqa , Jordan (2012)
Position Senior Environmental Engineer
Client Millennium Challenge Account - Jordan
Project Features
The project aims at implementing the outcomes of the resettlement action plan that was conducted previously for the water and wastewater projects in Zarqa Governorate, Jordan, this includes compensation for land acquisition and right of way cases within the project area for the identified project affected persons (PAPs)
Activities
Field visits to consultations with affected peoples and reaching final agreements. The work also includes the coordination of the projects negotiations and grievances committees.
Preliminary Environmental Impact Assessment(EIA) for10MW Solar PV Power Project in Ma’an (2013)
Client :Sun Edison
Preliminary Environmental Impact Assessment(EIA) for 50MW Solar PV Power Project in Safawi (2014)
Client :Modern Arabia for Solar Energy (MASE)
Preliminary Environmental Impact Assessment(EIA) for 50MW Solar PV Power Project in Safawi (2014)
Client: Abengoa Solar
Position :Technical Leader
Project Features
Preparation of a comprehensive Preliminary Environmental Impact Assessment, for PV Solar Power Project in Ma’an.
Activities
Preparing all the study sections of the Preliminary Impact Assessment study such as, Regulatory Frame work, project site baseline, Preliminary TOR, and Recommendations.
Environmental Impact Assessment (EIA) for Sulphur Recovery Unit Project in Jordan Petroleum Refinery Co.Ltd., Jordan (2012-2013)
Position: Project Manager Assistant and Technical Leader
Client: Le Gaz Integral
Project Features
Preparation of a comprehensive Environmental Impact Assessment, Sulphur Recovery Unit Project in Jordan Petroleum Refinery Co.Ltd
Activities
Managing the air quality monitoring program for the project, analyzing climate data as part of the baseline study, preparation of the water resources baseline and assessment section, preparation of a comprehensive Water Management Plan for the project, and proposing appropriate mitigation measures, and disposal methods for potential waste. In addition to provide project management support throughout the project lifecycle cost.
Environmental, Social, Health Impact Assessment (ESHIA) for Jordan Field Experiment (JFE) Project, Jordan (2011-2012)
Position:Senior Water and Environmental Engineer
Client: Jordan Oil Shale Company (JOSCO) – Subsidiary of Royal Dutch Shell.
Project Features
Preparation of a comprehensive Environmental, Social and health Impact Assessment, for a field experiment in Daba’a area, Jordan in order to test Shell’s oil shale In-Situ Conversion (ICP) process technology.
Activities
Managing the air quality monitoring program for the project, analyzing climate data as part of the baseline study, preparation of the water resources baseline and assessment section, preparation of a comprehensive Water Management Plan for the project, and proposing appropriate mitigation measures, and disposal methods for potential waste. In addition to provide project management support throughout the project lifecycle.
Environmental Impact Assessment (EIA), Social Impact Assessment (SIA), and a Health, Safety and Environmental Management System (HSE-MS) Resettlement Action Plan (RAP), and Remediation Plan for oil shale mining and oil shale fired power production in Jordan, (2011-2012)
Position: Senior Water and Environmental Engineer
Client: Pöyry Management Consulting Oy/Attarat Power Company (APCO)
Project Features
Preparation of a comprehensive Environmental Impact Assessment, HSE-MS and a resettlement action plan for a mining and power plant project in Attarat Um Ghudran, Jordan.
Activities
Managing the air quality monitoring program for the project, as part of the baseline study, preparation of EIA report, assessment of potential surface water and ground water impacts, review of surface water modeling and ground water modeling reports. In addition to client liaison and project management support.
Consultancy Services for the Preparation of the Feasibility Study, Environmental and Social Impact Assessment and Detailed Designs and Bidding Documents for Zarqa Governorate Wastewater System Reinforcement and Expansion, Zarqa- Jordan,( 2010- 2012)
Position: Senior Design Engineer
Client: Millennium Challenge Corporation & of Water & Irrigation / Water Authority of Jordan (MWI/ WAJ) funding by Millennium Challenge Corporation (MCC)
Project Features
the study is divided into two stages: Stage I: includes preparatory studies that are required to define an investment program; preliminary environmental and social assessment; preliminary designs; and the assessment of feasibility of the investment program, including economic analysis. Stage II: includes option 1: the preparation of Detailed Environmental and Social Impact Assessment (DESIA), option 2: Detailed Design and Contract Documents for five wastewater networks contracts (East Zarqa Zone, West Zone – Zarqa, West Zone – Russeifa, Hai Al AmeeraHaya-WZPS Zone, Sukhneh PS Zone) in addition to Wastewater Pump Stations Rehabilitation and Expansion contracts for (East Zarqa (EZPS), West Zarqa (WZPS), Adahya PS, Sukhneh, (SKPS), Hiteen Camp PS)
Activities
Designing& planning 50 km wastewater networks including house connections using in-house excel sheet, sewer layout.
Environmental Impact Assessment for Red - Dead Sea Jordan Project, Amman- Jordan (2010-2011).
Position: Head of the Regional Water Department
Client: Jordan Valley Authority – Ministry of Water and Irrigation.
Project Features
The project includes the studying of Environment impact assessment, social impact assessment and feasibility study of Dead Red Canal Project from the Jordanian side, the study should be submitted in Draft, Draft Final and Final stages, JVA scope of work was to review these documents and marks the comments.
Activities
Review the social Impact assessment report and mark the comments.
Preparation of the Feasibility Study, Detailed Design and Tender Documents and Supervision Services for the Construction of Wadi Zarqa Wastewater Closed Canal, Amman-Jordan,
Position: Senior Sanitary Engineer
Client: Ministry of Water and Irrigation / Water Authority
Project Features
The project includes the Study, Design and Construction Supervision Services. The total population of the areas to be served is around 1,000,000 persons, covering an area of of Amman and Zarqa governorates with the total length of the sewerage network is around 60 km with about 3m diameter .The project will be divided into five contracts each with a value of MS-M20 U.S. $. After the end of this project all Wastewater in Amman And 60% of Zarqa will be collected in one closed canal to be treated in As Samara Wastewater Treatment Plant.
Activities
Review Previous Studies for Water and wastewater master planning, Data collection, wastewater projection, prepare Inception and conceptual Reports, and Canal route layout .
Sana’a Sanitation Network Project Phase-II & Phase-III, Yemen.
Position: Sanitary Design Engineer
Client: Sana’a Sanitation and Water Local Cooperation
Project Features
The project includes the Study, Design and Construction Supervision Services. The total population of the areas to be served is around 520,000 covering an area of 3861 ha. Phase II of the project cover 10 areas while Phase III covers 6 additional areas. The total length of the sewerage network is around 940 km and design of Septage Tanks WWTP to serve parts of Sana’a in Yemen. .The project will be divided into different contracts each with a value of MS-M10 U.S. $. After the end of this project about 50 - 60 % of the occupied areas of the Capital Sana’a, and all the collected sewage are disposed and treated at the existing Treatment Plant at Rawda area near the International Airport of Sana’a are served by sewerage services.
Activities
Conducting the Design of sewers and preparing the BOQ.
Study & Design for Scatted Sanitation System – Amman, Jordan
Position: Project Manager
Client: Miyahuna
Project Features
Study the service for some areas and new districts or complete the service for the new buildings that are not connected to the network, in order to be connected to the existing sanitation network in Amman with about 90 km length.
Activities
Site Verification Planning the Service route and Manager the team Tasks.
Southern Amman Sanitation Networks Project (9 Sites), Jordan.
Position: Sanitary Design Engineer
Client: Ministry of Water and Irrigation / Water Authority of Jordan
Project Features
The services include Updating of Studies and Design and then Construction Supervision of Sanitation Networks, Main Lines and Branches and House Connections, and Preparation of Tender Documents in 9 sites in southern Amman. The length of the Network is 400km and 5000 house connections .
Activities
Planning, Design, Site Verification and preparing the BOQs
Water Supply and Sewerage Services to the Metolong Dam Camp and Adjacent Areas, Lesotho
Position: Sanitary / Process Engineer
Client: Water and Sewerage Authority
Project Features
The project involves the construction of a roller compacted concrete dam some 60m in height with a crest length of 210m. The dam site is located in the Maseru District, adjacent to the villages of ha Seeiso and Metlong Ha Makotoko on the South Phuthiatsana River, some 35km from Maseru. The storage area extends upstream to the village of Honamoleli in Berea district, approximately 16 km from the dam site. Ancillary works include the construction of some 88.5 km of the transmission mains, associated pump stations and reservoirs, and a water treatment plant adjacent to the dam.The Metolong Dam site is surrounded by a number of villages some of which already have existing water supply and sanitation facilities whilst some require these services.
Activities
Planning, Design, Site Verification and preparing the BOQs
Seven Cities Project for Water supply & Networks, Sewerage Networks & WWTPs –Yemen.
Position: Process & Sanitary Design Engineer
Client: Sana’a Sanitation and Water Local Cooperation
Project Features
The project entails the development of new water resources that should fulfill the domestic requirements of the secondary seven cities in Yeman; Al Ghaida, Ma’erb, Al Jouf, Dhamar, Attq, Al Baida and Maa’bar. Water resources are mainly groundwater with different depths. The second part of the project consists of designing the water supply and wastewater collection and several Wastewater Treatment Plants systems for the said cities. The project started on May 2005 and will last for 18 months. The project is financed by the World Bank.
Activities
Planning, Design, Site Verification and preparing the BOQs
Construction of Hai Nazzal Secondary School, Amman, Jordan, 2006 – 2007
Position: Site Engineer
Client: Ministry of Public Works and Housing
Project Features
Theschool total area 1600 m2 as a building in addition to about 5000 m2 of open areas , also the project includes a Water Tank and a 150 m’ retaining Wall.
Activities
Follow up and acceptance of the building process activities
Paper Recycling Project in Abu Dhabi city and Abu Dhabi Environmental City, Abu Dhabi,UAE.
Position: Project Manager
Client: Zayed Foundation
Project Features
The project includes built up a a paper recycling system in Abu Dhabi city reach all levels, basically schools and academic institutes , the residential buildings specially towers and finally commercial buildings, after start the project the environment friends society can finance themselves by sale the collected paper.
Activities
Follow up and manage all project activities including preparing awareness seminars and workshops, courses about environment and recycling issues
Al Zaytoonh Privet University, Amman, Jordan.
Position:Project Engineer
Client: Al Zaytoonh Privet University
Project Features
The project includes biological design and built a wastewater treatment plant for the sewerage of the university with capacity about 150m3/day , the design should be included primary, secondary and tertiary treatment the effluent should be meet the Jordanian standards for irrigation purpose.
Activities
Follow up and manage all project activities including process design and electrometrical selection then construction, commission and hand out as well as sampling of the effluent.
Applied Science Privet University Wastewater Treatment Plant, Amman, Jordan.
Position: Project Engineer
Client: Applied Science Privet University
Project Features
The project includes biological design and built a wastewater treatment plant for the sewerage of the university with capacity about 100m3/day , the design should be included primary, secondary and tertiary treatment the effluent should be meet the Jordanian standards for irrigation purpose.
Activities
Follow up and manage all project activities including process design and electrometrical selection then construction, commission and hand out as well as sampling of the effluent.
Al Tahoonh Slaughter House WWTP, Zarqa, Jordan.
Position: Project Engineer
Client: Al Amira Company
Project Features
The project includes biological design and built a wastewater treatment plant for the sewerage of Al Tahouna slaughter house with capacity about 250m3/day, the design should be included DAF unit as a pretreatment and aerobic secondary treatment, the effluent should be meet the Jordanian standards for wadi discharge purpose.
Activities
Follow up and manage all project activities including process design and electrometrical selection then construction, commission and hand out as well as sampling of the effluent.
Gray Water Treatment System, Karak, Jordan.
Position: Project Engineer
Client: WEIPIA/ USAID
Project Features
The project includes simple affordable design and built for gray water treatment unitsfor about 40house inn Al Sqira town, the capacity for each unit is about 7 m3/day depends on number of residences in each house.
Activities
Follow up and manage all project activities including process design and electrometrical selection then construction, commission and hand out as well as sampling of the effluent.
Al Shawahed Wells Water Treatment Plant, Jerash, Jordan.
Position :Project Engineer
Client: Ministry of Water and Irrigation / Water Authority of Jordan
Project Features
The project includes water treatment plant for about 120 m3/day for three wells in al Shwaeid area.
Activities
Follow up and manage all project activities including process design and electrometrical selection then construction, commission and hand out as well as sampling of the effluent.